return to CARE

CARE Deliverables
(23/04/2009)

return to CARE

 

2004 2005 2006 2007 2008

 

2004

Activity

Deliverable N°

Deliverable Name

Deliverable Type

Workpackage/Task N°

Delivered by Contractor (s)

Planned    (in months)

Achieved  (in months)

ELAN

1

ELAN web site

Web site

All WPs

CNRS-Orsay

4

4

ELAN

2

Beam Dynamics code repository site functional

Data base

WP3

CERN

12

12

ELAN

3

Instrumentation web site

Web site

WP4

STFC, UMA

6

21

ELAN

4

Instrumentation data base

Data base

WP4

STFC, UMA

12

23

BENE

5

BENE web site

Web site

All WPs

INFN-Na

4

4

BENE

6

Annual report of the BENE network

Report

All WPs

INFN-Na

12

12

BENE

7

Proposal for FP6 Design Study of a new neutrino facility

Report

All WPs

INFN-Na

12

delayed to FP7

BENE

8

Proceedings of Multi-MW workshop

Report

All WPs

INFN-Na

12

14

BENE

9

BENE Physics web site

Web site

WP1

INFN-Pa, CERN

3

3

HHH

10

HHH web site

Web site

All WPs

CERN

12

9

HHH

11

APD web site

Web site

WP3

CERN

6

9

SRF

12

Final report on reliability issues

Report

WP2

DESY

9

30

SRF

13

EP on samples: best EP parameters

Report

WP5

CEA

12

26

NED

14

Final report on wire and cable specifications

Report

WP3

CERN

6

6

NED

15

Design report on 15 T dipole magnet

Report

WP3

CERN

12

13

 


2005

Activity

Deliverable N°

Deliverable Name

Deliverable Type

Workpackage/Task N°

Delivered by Contractor (s)

Planned    (in months)

Achieved  (in months)

ELAN

1

Work plan and documentation data base

Data base

WP1

CERN

24

22

ELAN

2

Data base on SRF documents

Data base

WP2

DESY

24

24

BENE

3

18-month interim report

Report

All WPs

INFN-Na

23

23

BENE

4

Annual report of the BENE network

Report

All WPs

INFN-Na

24

24

BENE

5

Proceedings of NuFact’05 workshop

Report

All WPs

INFN-Na

24

30

BENE

6

Launch of scoping study of a new neutrino facility

Web site

Report

All WPs

INFN-Na

18

18

HHH

7

Beam Dynamics code repository

Data base

WP3

CERN

24

18

SRF

8

EP on multi-cells: parameters fixed

Report

WP5

DESY

13

37

SRF

9

Automated EP is defined

Report

WP5

INFN-Legnaro

21

37

SRF

10

Dry ice cleaning: parameters fixed

Report

WP5

DESY

18

37

SRF

11

CEA tuner: start of integrated experiments

Prototype

WP8

CEA

15

24

SRF

12

Report on IN2P3 tuner activities

Report

WP8

CNRS-Orsay

24

39

SRF

13

Report on data management developments

Report

WP9

DESY

21

24

SRF

14

Report on RF gun control tests

Report

WP9

DESY

23

37

PHIN

15

High efficiency photocathode comparison

Report

WP2

FZR

24

24

PHIN

16

High power laser oscillator

Report

WP3

STFC-RAL

13

13

PHIN

17

Amplifier construction

Prototype

WP3

CERN, INFN

19

54

PHIN

18

Oscillator + amplifier test

Report

WP3

STFC-RAL

23

30

PHIN

19

Pulse shaping system: phase mask acquisition and test

Report

WP3

INFN-Milano

16

23

PHIN

20

Pulse shaping system: Dazzler acquisition and test

Report

WP3

INFN-LNF

17

41

PHIN

21

Pulse shaping comparison

Prototype

WP3

INFN-LNF,

INFN-Milano

22

47

PHIN

22

UV harmonic generator test

Prototype

WP3

CERN, CEA

16

54

PHIN

23

Laser RF feedback development

Report

WP3

CERN

21

59

PHIN

24

Two 3 GHz RF guns construction

Prototype

WP4

CNRS-Orsay

18

54

PHIN

25

1-50 MeV spectrometer construction

Prototype

WP4

CNRS-LOA

24

36

HIPPI

26

Halo measurement device design and construction

Report

WP5

CERN

18

24

NED

27

Commissioning of heat transfer facility

Prototype

WP2

CEA, WUT

16

35

NED

28

Final report on Quench Protection

Report

WP2

INFN-Milano

18

23

NED

29

Report on conventional insulation

Report

WP4

STFC-RAL

24

40

NED

30

Report on innovative insulation

Report

WP4

CEA

18

48

 


2006

Activity

Deliverable N°

Deliverable Name

Deliverable Type

Workpackage/Task N°

Delivered by Contractor (s)

Planned (in months)

Achieved (in months)

ELAN

1

Data base on diagnostics performance

Data base

WP4

STFC, UMA

36

36

BENE

2

Annual report of the BENE network

Report

All WPs

INFN-Na

36

38

BENE

3

Proposal for design studies and R&D

Report

All WPs

INFN-Na, CCLRC

36

31

BENE

4

Summary of NuFact’06 workshop

Strategy document

Web site

Report

All WPs

INFN-Na

36

32

HHH

5

Data base on SC magnets and cables

Data base

WP1

CERN

36

48

SRF

6

Evaluation of spinning parameters

Report

WP3

INFN-Legnaro

29

37

SRF

7

1-cell spinning parameters defined

Report

WP3

INFN-Legnaro

36

57

SRF

8

Report on new LLRF hardware components

Report

WP9

DESY

26

37

SRF

9

New BPM ready for installation

Prototype

WP11

CEA

25

34

SRF

10

Evaluation of HOM-BPM operation

Report

WP11

CEA

36

37

PHIN

11

Photocathode ready for 3 GHz RF guns

Prototype

WP2

CERN

25

41

PHIN

12

UV generation and feedback: overall system assembly and tests

Prototype

WP3

CERN

30

58

PHIN

13

SC RF gun realisation

Prototype

WP4

FZR

26

36

PHIN

14

SC RF gun test

Report

Report

WP4

FZR

36

part 1: 39 final : 59

PHIN

15

CTF3 3 GHz RF gun test at CERN

Report

WP4

CNRS-Orsay, CERN

33

60

HIPPI

16

H-mode DTL prototype ready

Prototype

WP2

IAP-FU

36

54

HIPPI

17

CCDTL prototype tested

Report

WP2

CERN

36

47

HIPPI

18

Elliptical cavities: cavity B ready

Prototype

WP3

CEA

30

41

HIPPI

19

Chopping structure A: prototype ready

Prototype

WP4

CERN

32

36

HIPPI

20

Beam Dynamics: simulations and experiments at UNILAC

Report

WP5

GSI

36

46

HIPPI

21

Profile measurements by fluorescence

Report

WP5

GSI

31

38

HIPPI

22

Non interceptive bunch measurement

Report

WP5

GSI

36

42

HIPPI

23

Collimators design

Report

WP5

CERN

36

30

NED

24

Final Report on Heat Transfer Measurements

Report

WP2

CEA

36

47

NED

25

Final wire production

Prototype

Report

WP3

CERN

30

60

NED

26

Final report on wire characterization

Prototype

Report

WP3

CERN

30

60

NED

27

Final cable production

Prototype

WP3

CERN

36

60

NED

28

Final report on cable performances

Report

WP3

CERN

36

60


2007

Activity

Deliverable N°

Deliverable Name

Deliverable Type

Workpackage/Task N°

Delivered by Contractor (s)

Planned (in months)

Achieved (in months)

ELAN

1

Data base on laser plasma acceleration

Data base

WP5

CRNS-LPGP

48

cancelled

BENE

2

Annual report of the BENE network

Report

All WPs

INFN-Na

48

48

BENE

3

Proposal for design studies and R&D

Report

All WPs

INFN-Na

48

48

BENE

4

Proceedings of NuFact’07 workshop

Web site

Report

All WPs

INFN-Na

48

60

SRF

5

Fabrication of new cavity with improved components

Prototype

WP2

INFN

47

59

SRF

6

EB Welding of prototype components

Prototype

WP2

DESY

48

57

SRF

7

Fabrication Multi-cell cavities by spinning

Prototype

WP3

INFN-Legnaro

48

60

SRF

8

Fabrication of hydroformed 9-cell cavities

Prototype

WP3

DESY

47

60

SRF

9

First multicell coating with linear-arc cathode

Prototype

WP4

IPJ

48

60

SRF

10

First multicell coating with planar-arc cathode

Prototype

WP4

INFN-Roma2

41

60

SRF

11

Report on quality of HTc superconducting properties

Report

WP4

INFN-Roma2

48

59

SRF

12

EP on single cells: parameters fixed

Report

WP5

CEA

48

57

SRF

13

Evaluate oxipolishing experiments

Report

WP5

DESY

40

60

SRF

14

Final report on industrial electropolishing

Report

WP5

DESY

48

59

SRF

15

Automated EP: Conclude on best electrolyte

Report

WP5

INFN-Legnaro

44

59

SRF

16

VT cleaning of 9-cell cavities: evaluation of experimental results

Report

WP5

DESY

48

60

SRF

17

Dry ice cleaning of horizontal 9-cell cavities: evaluation of experimental results

Report

WP5

DESY

48

60

SRF

18

Final report on SQUID scanning

Report

WP6

DESY

48

57

SRF

19

Conclude on comparison of SQUID scanner vs. flux gate detector

Report

WP6

INFN-Legnaro

48

59

SRF

20

DC field emission: evaluation of scanning results

Report

WP6

DESY

48

51

SRF

21

DC field emission: evaluate strong emitter investigations

Report

WP6

DESY

48

51

SRF

22

Prototype couplers: final report on conditioning

Report

WP7

CNRS-Orsay

47

59

SRF

23

Evaluation of INFN tuner operation

Report

WP8

INFN-Mi

48

51

SRF

24

Cryostat integration tests: final evaluation

Report

WP10

CEA

46

60

SRF

25

Evaluation of BPM operation

Report

WP11

CEA

48

48

SRF

26

Evaluation of beam emittance monitor operation

Report

WP11

INFN-Ro

48

59

PHIN

27

Superconducting cavity photocathode tests

Report

WP2

FZR

37

59

PHIN

28

Final report on 100 MeV laser driven plasma source R&D

Report

WP2

CNRS-LOA

48

47

PHIN

29

NEPAL 3 GHz RF gun test at Orsay

Report

WP4

CNRS-Orsay

37

59

PHIN

30

50 MeV (low energy) spectrometer test

Report

WP4

CNRS-LOA

42

36

PHIN

31

1 GeV spectrometer development

Report

WP4

CNRS-LOA

48

47

HIPPI

32

Drift Tube Linac: development of critical components

Report

WP2

CNRS-LPSC

37

46

HIPPI

33

Side Couple Linac: RF cold model prototype test

Report

WP2

CNRS-LPSC, CERN

48

52

HIPPI

34

Elliptical cavities: test stand ready

Test stand

WP3

CEA

39

47

HIPPI

35

Spoke cavities: prototype ready

Prototype

WP3

FZJ, CNRS-Orsay

46

54

HIPPI

36

Chopper structure A: prototype testing (w/o and with beam)

Report

WP4

CERN

44

57

HIPPI

37

Chopper line: Beam line assembly and measurements

Report

WP4

CERN

48

60

HIPPI

38

Chopper structure B: prototype ready

Prototype

WP4

STFC-RAL

42

54

HIPPI

39

Diagnostics and collimation: online transmission control

Report

WP5

GSI

46

52

HIPPI

40

Diagnostics and collimation: beam profile monitor for high intensity

Report

WP5

FZJ

42

46

 


2008

Activity

Deliverable N°

Deliverable Name

Deliverable Type

Workpackage/Task N°

Delivered by Contractor (s)

Planned (in months)

Achieved (in months)

ELAN

1

Final report of the ELAN network

Report

All WPs

CNRS-Orsay

60

60

BENE

2

Final report of the BENE network

Report

All WPs

INFN-Na

60

60

BENE

3

Proposal for design studies and R&D

Report

All WPs

INFN-Na

60

60

BENE

4

Proceedings of NuFact’08 workshop

e-Proceedings

All WPs

INFN-Na

60

60

HHH

5

Final report of the HHH network

Report

All WPs

CERN

60

60

HIPPI

6

Drift Tube Linac: Optimised design

Report

WP2

CNRS-LPSC, CEA, CERN

60

60

HIPPI

7

H-mode Drift Tube Linac: design finished

Report

WP2

IAP-FU

60

60

HIPPI

8

Cell Coupled Drift Tube Linac: design finished

Report

WP2

CERN

54

56

HIPPI

9

Comparative assessment of Normal Conducting structures

Report

WP2

CNRS-LPSC, CEA, CERN, IAP-FU

60

60

HIPPI

10

Elliptical cavities: high power pulsed tests cavity A and B

Report

WP3

CEA, INFN-Mi

60

60

HIPPI

11

Spoke cavities: testing of prototype

Report

WP3

FZJ, CNRS-Orsay

60

60

HIPPI

12

CH resonator: measurements

Report

WP3

IAP-FU

60

60

HIPPI

13

Comparative assessment of superconducting structures

Report

WP3

CEA, INFN-Mi, FZJ, IAP-FU, CNRS-Orsay

60

60

HIPPI

14

Chopper structure B: prototype testing

Report

WP4

STFC-RAL

54

54

HIPPI

15

Comparative assessment of chopper designs

Report

WP4

CERN, STFC-RAL

58

60

HIPPI

16

Beam Dynamics: code benchmarking

Report

WP5

GSI et al.

58

58

HIPPI

17

Simulations and experiment at CERN

Report

WP5

CERN

60

60

HIPPI

18

Comparative assessment of dynamics and measurements

Report

Report

WP5

GSI et al.

60

60